Featured News
Posted February 9, 2023
The East County Advanced Water Purification Program recently received a funding allocation for an additional $2.4 Million. The funding was part of the recent 2023 Omnibus Appropriation Package passed by Congress and signed by the President. &...
Read on...
News Flash
Posted on: March 13, 2023
The Joint Powers Authority awarded Phase 1A work to Anaergia for the Progressive Design-Build-Operate-Maintain Agreement for the energy recovery element of this project - Package 5. Package 5 is the energy recovery operations of the Program. Bio...
Read on...
Benefits and Information News
Posted on: February 7, 2023
As part of Construction Package 3, Horizontal Directional Drilling is beginning in order to install wastewater pipelines below Carlton Oaks Golf Course and north to Santee Lakes. This technology will allow the pipeline to go in without trenching...
Read on...
Benefits and Information News
News Flash
Posted on: March 13, 2023
Design and construction activities for Package 4 will continue now with the Phase 1B Amended and Restated Progressive Design-Build Agreement with Orion Construction approved by the JPA in March 2023. Package 4 will install a Regional Brine Line ...
Read on...
Home
Posted on: February 9, 2023
The East County Advanced Water Purification Program recently received a funding allocation for an additional $2.4 Million. The funding was part of the recent 2023 Omnibus Appropriation Package passed by Congress and signed by the President. &...
Read on...
Home
Posted on: January 16, 2023
Starting in January, concrete trucks will be arriving at the main construction site early in the morning to pour concrete at the main project construction site north of Santee Lakes. These early morning pours will begin at approximately 4:00 am....
Read on...
Home